 Estimated Date  Construction Activity
 Jan - Jun 2017  Utilities relocation and Park Drive realignment
 Jul - Dec 2017  Shoring
 Sep 2017 - Jan 2018  Excavation
 Nov 2017 - Jul 2018  Wall construction
 Feb 2018 - Oct 2018  Structures, mechanical and lighting work
 Jul 2018 - Jan 2019  Site work and landscaping
 Feb 2019  Mini park, sidewalk and street improvements