Fields Tear-Out Started, July 2017
The street modification portion of the project began in March 2017. The league bid farewell to the old fields on July 8. The current status of the McKelvey Park Detention Basin project is on this information page.Estimated Date | Construction Activity |
Jan - Jun 2017 | Utilities relocation and Park Drive realignment |
Jul - Dec 2017 | Shoring |
Sep 2017 - Jan 2018 | Excavation |
Nov 2017 - Jul 2018 | Wall construction |
Feb 2018 - Oct 2018 | Structures, mechanical and lighting work |
Jul 2018 - Jan 2019 | Site work and landscaping |
Feb 2019 | Mini park, sidewalk and street improvements |